FERC approves MARA deal for Long Ridge gas-fired power assets

FERC approves MARA deal for Long Ridge gas-fired power assets

N
News Editor
2026-11-05 01:46:24
The U.S. Federal Energy Regulatory Commission has approved MARA Holdings’ acquisition of the Long Ridge natural gas power assets, according to Matthew Sigel, head of digital assets research at VanEck. The case is listed as EC26-92. Sigel said objections raised by the Independent Market Monitor, citing issues related to BlackRock and Vanguard, were not upheld. FERC also declined to make continued power supply from the plant into the PJM grid a condition of approval. Sigel’s breakdown values the transaction at about $1.512 billion. That figure covers roughly 0.5 gigawatts of gas-fired generation capacity, including 485 megawatts of approved output and 505 megawatts of nameplate capacity, along with about $144 million in annualized adjusted EBITDA. On that basis, the deal implies a valuation multiple of about 10.5x. He added that recent PJM gas generation transactions have been valued at around 7x, implying the plant itself is worth about $1 billion, with roughly $500 million of premium tied to land, gas wells, rail access and expansion options. MARA is set to retain about $900 million of Long Ridge debt and pay another roughly $610 million in cash, which Sigel said the company plans to cover with a bitcoin-backed loan of about $600 million drawn in August. The outside date for the transaction is Nov. 30.

The U.S. Federal Energy Regulatory Commission, or FERC, has approved MARA Holdings’ acquisition of the Long Ridge natural gas power assets, according to Matthew Sigel, head of digital assets research at VanEck. The case number is EC26-92.

Objections were rejected in the approval process

Sigel said objections raised by the Independent Market Monitor, or IMM, on grounds related to BlackRock and Vanguard were not supported. He also said FERC rejected a proposal to make continued power supply from the plant to the PJM grid a condition of approval.

Deal value and asset breakdown

Based on Sigel’s breakdown, the transaction carries an enterprise value of about $1.512 billion. That corresponds to roughly 0.5 gigawatts of gas-fired generation capacity, including 485 megawatts of approved output and 505 megawatts of nameplate capacity, as well as about $144 million in annualized adjusted EBITDA. The implied valuation multiple is about 10.5x.

Sigel said recent PJM gas generation transactions have been valued at around 7x. Using that benchmark, he estimated the plant itself at about $1 billion, with roughly $500 million of premium tied to land, gas wells, rail infrastructure and expansion options.

Funding plan and deadline

MARA will retain about $900 million of Long Ridge debt and will also need to pay about $610 million in cash. Sigel said the company plans to cover that with a roughly $600 million bitcoin-backed loan drawn in August. The outside date for the deal is Nov. 30.

AI load and unresolved points

Sigel also said MARA referenced about 600 megawatts of total AI load at the site, including about 200 megawatts of existing grid-connected load.

It remains unclear whether the expansion will move forward through a joint venture with Starwood, and whether MARA will be able to retain up to a 50% stake. Sigel said the next catalyst could be a lease signed around the time of closing.

This article was originally published by Bit.Fan. For more cryptocurrency news and market insights, visit www.bit.fan.
4600

Disclaimer:

The market information, project data, and third-party content displayed on this platform are for industry information sharing only and do not constitute any form of investment advice or return commitment.

Cryptocurrency trading carries high risks. Users should fully assess their risk tolerance and make independent decisions. All profits, losses, and legal responsibilities are borne by the users themselves.

FERC approves MARA deal for Long Ridge gas-fired power assets | Bit.Fan