Finland orders Google to halt data center site work after 530 hectares of forest were cleared before environmental review
Finnish authorities have ordered Google to stop preparatory work at two planned AI data center sites after roughly 530 hectares of forest were cleared before environmental impact assessments were completed. The sites are in Muhos and Otanmäki, a former mining village in Kajaani, and form part of Google’s €13 billion data center investment in Finland announced on Sept. 9. Google told Finnish public broadcaster Yle that about 330 hectares were cleared in Muhos and just under 200 hectares in Otanmäki. The Regional State Administrative Agency for Northern Finland, referred to in the report as LVV, said the projects could not rely solely on the Forest Act because the land is being converted for data center construction rather than restored as forest. Officials also said the work went beyond logging and included stripping topsoil, building access roads and altering drainage before the environmental review process had finished. Google has said it acted under its understanding of Finnish law and confirmed it would comply with the stop-work order. Claims that wolves moved into nearby villages after the clearing have circulated online, but publicly cited national data only show that Finland’s wolf population and observation reports were already rising, leaving no direct basis to confirm a causal link from this single case.