Morgan Stanley says U.S. data centers could face a 32 GW power shortfall by 2028

Morgan Stanley says U.S. data centers could face a 32 GW power shortfall by 2028

N
News Editor
2026-10-07 08:52:20
Morgan Stanley said in a new report that U.S. data centers are likely to face a net power shortfall of about 34% from 2026 to 2028, equivalent to 32 GW. The bank said the key constraint for the sector may shift from chip shortages to electricity shortages, with the pressure likely to hit the tail end of the supply chain first, including ASICs, memory, optical modules, power management and analog chips. It added that Nvidia and Broadcom are not expected to see a material change to their 2027 earnings forecasts because they have better visibility into final deployment locations and broader global exposure beyond the U.S. market. By contrast, ASICs are more sensitive to power access, while memory, optics and power-management products are more exposed to delays in data center projects, including deferred orders, cancellations and inventory adjustments. Morgan Stanley pointed to Oracle’s 1.3 GW Project Lighthouse in Wisconsin as a real-world example of the risk, saying full-power delivery could slip to October 2028 at the earliest and to spring 2029 in a more pessimistic case.

BlockBeats reported on Oct. 7 that Morgan Stanley said in its latest report that U.S. data centers are expected to face a net power shortfall of about 34% from 2026 to 2028, equivalent to 32 GW.

Power constraints may overtake chip shortages

The report said the main bottleneck for data centers may shift from a lack of chips to a lack of electricity. Morgan Stanley said the change would first hit the tail end of the supply chain, including ASICs, memory, optical modules, power management and analog chips.

The bank said Nvidia and Broadcom are not expected to see a material impact on their 2027 earnings forecasts. It attributed that to stronger visibility into where chips will ultimately be deployed, along with global footprints that reduce dependence on the U.S. market alone.

ASICs, by comparison, are more sensitive to access to power resources. Memory, optical and power-management products are more vulnerable to delays in data center projects, facing risks that include deferred orders, cancellations and inventory adjustments.

Oracle project cited as a live example

Morgan Stanley said Oracle’s 1.3 GW Project Lighthouse in Wisconsin has already become a real-world reflection of that risk. Full-power delivery for the project could be delayed until October 2028 at the earliest, and in a pessimistic scenario, it could slip to spring 2029.

The report added that even if AI servers have already been installed in racks, they cannot be turned into actual computing capacity or revenue without sufficient power.

New supply still falls short

Morgan Stanley estimated that new U.S. gas turbine and engine capacity will reach about 19 GW under its base-case scenario from 2026 to 2028. Bloom Energy fuel cells are expected to contribute about 6 GW, while nuclear power and retrofits of crypto mining sites may add further support, but the total still would not be enough to close the gap.

At the same time, overseas expansion faces limits from permitting and geopolitical factors, making it hard to shift demand abroad quickly.

This article was originally published by Bit.Fan. For more cryptocurrency news and market insights, visit www.bit.fan.
200

Disclaimer:

The market information, project data, and third-party content displayed on this platform are for industry information sharing only and do not constitute any form of investment advice or return commitment.

Cryptocurrency trading carries high risks. Users should fully assess their risk tolerance and make independent decisions. All profits, losses, and legal responsibilities are borne by the users themselves.